What are the documents required to apply for this scheme?

The documents required are as follows:

i. Memorandum & Articles of Association of applicant
ii. Attachment - certified copy of Form 9, 24, 49
iii. Collaboration / joint venture agreement with other project partner(s), authorisation letter from technology provider
iv. Approved layout drawing indicating the project boundary
v. Project Management Team structure
vi. Team member CV, employment contract or latest EPF receipts as evidence of employment
vii. Full technology specification, track record, relevant approved engineering drawings etc.
viii. Project implementation schedule and key milestones (if indicated in separate sheet)
ix. Please provide necessary approval document (if required for project implementation)
x. i.e. Environment Impact Assessment,
xi. Sales and Purchase Agreement,
xii. Tenancy Agreement, Development order,
xiii. Safety, Fuel Supply Agreement etc.
xiv. Calculation of project outcome
xv. Soft Copy of the spreadsheet for calculation of cash flow and IRR (with relevant supporting document)
xvi. Relevant approved drawings to support explanation